    8 men and 12 children can do a work in 9 days. A child takes double the time to do a work than the man, In how many days 12 men can complete double the work?

    A)  \[10\frac{1}{2}\] days

    B)  14 days

    C)  \[16\frac{1}{2}\]days   

    D)  21 days

    Correct Answer: D

    Solution :

    1 man = 2 children; because a child takes double time to do work than the man. \[\therefore \]8 men + 12 children = 8 + 6 = 14 men \[\because \]14 men can do a work in 9 days. \[\therefore \]12 men can do the same work in \[\frac{14\times 9}{12}\]days \[\because \]12 men can do twice the work in\[\frac{14\times 9\times 2}{12}=21\]