    A and B together can complete a task in 20 days. B and C together can complete the same task in 30 days.  A and C together can complete the same task in 40 days. What is the respective ratio of the number of days taken by A when completing the same task alone to the number of days taken by C when completing the same task alone?

    A) 2: 5                              

    B) 2: 7  

    C) 3: 7                              

    D) 1: 6

    E) 3: 5

    Correct Answer: D

    Solution :

    \[(A+B)'s\] 1 day's work \[=\frac{1}{20}\]
    \[(B+C)'s\] 1 day's work \[=\frac{1}{30}\]
    \[(C+A)'s\] 1 day's work \[=\frac{1}{40}\]
    On adding,
    \[2(A+B+C)'s\] 1 day's work \[=\frac{1}{20}+\frac{1}{30}+\frac{1}{40}\]
    \[=\frac{6+4+3}{120}=\frac{13}{120}\]
    \[\therefore \] \[(A+B+C)'s\]1 day's work \[=\frac{13}{240}\]
    \[\therefore \] As 1 day's work
    \[=\frac{13}{240}-\frac{1}{30}=\frac{13-8}{240}=\frac{5}{240}=\frac{1}{48}\]
    C's 1 day's work \[=\frac{13}{240}-\frac{1}{20}=\frac{13-12}{240}=\frac{1}{240}\]
    \[\therefore \] Required ratio \[=48:240=1:5\]