    A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then, A, B and C together can do the work in                   [SSC (CGL) 2011]

    A) \[28\,\,\text{days}\]                   

    B) \[14\,\,\text{days}\]

    C) \[5\frac{5}{7}\text{days}\]        

    D) \[\text{8}\frac{2}{7}\text{days}\]

    Correct Answer: C

    Solution :

    Given, (A + B)'s 1 day's work \[=\frac{1}{10}\]    … (i)
    (B + C)'s1 day's works \[=\frac{1}{6}\]                ... (ii)
    (C + A)'s 1 day's work\[=\frac{1}{12}\]                … (iii)
    On adding Eqs. (i), (ii) and (iii), we get
    2 (A + B + C)'s 1 day's work \[=\frac{1}{10}+\frac{1}{6}+\frac{1}{12}\]
                                        \[=\frac{6+10+5}{60}=\frac{21}{60}=\frac{7}{20}\]
    \[\Rightarrow \](A + B + C)'s 1 day's work \[=\frac{7}{40}\]
    \[\therefore \]All three together will complete the work in
                            \[=\frac{40}{7}=5\frac{5}{7}\,\,\text{days}\]