    A and B working separately can do a piece of work in 9 and 15 days, respectively. If they work for a day alternately with A beginning, then the work will be completed in

    A) 10 days            

    B) 11 days

    C) 9 days              

    D) 12 days

    Correct Answer: B

    Solution :

    Work done by A and B in 2 days \[=\frac{1}{9}+\frac{1}{15}=\frac{8}{45}\]
    Work done by both in 10 days \[=\frac{5\times 8}{45}=\frac{8}{9}\]
    Remaining work \[=1-\frac{8}{9}=\frac{1}{9}\]
    Next day, A will do the work.
    \[\therefore \]Work done by A in one day\[=\frac{1}{9}=\]remaining work
    Hence, total days required to complete the work
    = 11 days