    A and B working separately can do a piece of work in 10 days and 15 days, respectively. If they work on alternate days beginning with A, in how many days will the work be completed?                              [SSC (CPO) 2013, (CGL) 2003]

    A) 18                                

    B) 13

    C) 12        

    D) 6

    Correct Answer: C

    Solution :

    Work done by (A + B) in two days
    \[=\frac{1}{10}+\frac{1}{15}=\frac{3+2}{30}=\frac{5}{30}=\frac{1}{6}\]
    \[\therefore \]Work done by (A + B) in one day \[=\frac{1}{12}\]
    Hence, (A + B) can complete the work in 12 days,