    8 men can complete a piece of work in 20 days and 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the work?                                                                        [CBI (PO) 2010]

    A) 16        

    B) 12    

    C) 14                                

    D) 10

    E) None of these

    Correct Answer: A

    Solution :

    20 day's work of 8 men = 32 day's work of 8 women
    \[\Rightarrow \]One day's work of 160 men
    = 1 day's work of 256 women
    \[\Rightarrow \]               5M = 8W
    \[\therefore \]      5M and 8W = 16W
    \[\therefore \]                  \[\frac{8}{16}=\frac{x}{32}\]
    \[\Rightarrow \]               \[x=\frac{8\times 32}{16}=16\,\,\text{days}\]