    A completes a piece of work in 4 days and B completes it in 6 days. If both A and B work together, then the number of days required to complete the same work is                                                                            [BSSC (CGL) 2015]

    A) \[3\frac{4}{5}\,days\]                

    B) \[2\frac{3}{5}\,days\]

    C) \[2\frac{2}{5}\,days\]    

    D) \[3\frac{2}{5}\,days\]

    Correct Answer: C

    Solution :

    Total number of days required to complete the work
    \[=\frac{4\times 6}{4+6}=\frac{24}{10}=\frac{12}{5}=2\frac{2}{5}\,\,days\]