    12 men take 36 days to do a work while 12 women complete \[\frac{3}{4}th\] of the same work in 36 days. In how many days 10 men and 8 women together will complete the same work?

    A) 6                                 

    B) 27

    C) 12                                

    D) Data inadequate

    Correct Answer: B

    Solution :

    In 36 days 12 men can do 1 complete work.
    In 36 days 12 women can do \[\frac{3}{4}th\] of the work.
    Since, time and the number of persons is the same in both cases.
    1 woman's daily work \[=\frac{3}{4}th\] of 1 man's daily work
    8 women's daily work \[\frac{3}{4}\times 8=6\] men's daily work
    10 men + 8 women's dally work
    \[=\text{(10}\,\text{men}+\text{6}\,\text{men)}\]
    = 16 men's daily work
    \[\therefore \]12 men can do the work is 36 days,
    \[\therefore \]16 men can do the work \[=\text{36}\times \frac{12}{16}=27\,days.\]