    A and B can complete a piece of work in 18 days, B and C in 24 days and A and C in 36 days. In how many days, will all of them together complete the work?                                                           [NICL (AO) 2014]

    A) 16        

    B) 15

    C) 12                                

    D) 10

    E) 17

    Correct Answer: A

    Solution :

    \[(A+B)'s\] one day work \[=\frac{1}{18}\]                       ….(i)
     \[(B+C)'s\]one day work \[=\frac{1}{24}\]                       ….(ii)
    and \[(A+C)'s\] one day works \[=\frac{1}{36}\]    ….(iii)
    On adding Eqs. (i), (ii) and (iii), we get
    \[2\,(A+B+C)=\frac{1}{18}+\frac{1}{24}+\frac{1}{36}\]
    \[=\frac{4+3+2}{72}=\frac{9}{72}=\frac{1}{8}\]
    \[\Rightarrow \] \[(A+B+C)'s\] one day work \[=\frac{1}{2\times 8}=\frac{1}{16}\]
    So, A, B and C will together complete the work in
    16 days.