Banking Quantitative Aptitude Sample Paper Quantitative Aptitude Sample Paper-13

  • question_answer
    24 men can complete a piece of work in 15 days. 2 days after 24 men started working, 4 men left the work. How many more days will the remaining men now take to complete the remaining work?

    A) \[15\frac{3}{5}\]           

    B) \[16\frac{4}{5}\]

    C) \[11\frac{2}{5}\]                                   

    D) \[10\frac{4}{5}\]

    E) \[14\frac{1}{5}\]

    Correct Answer: A

    Solution :

    \[\frac{\text{Work}}{\text{Men}\times \text{Days}}=\frac{\text{Remaining}\,\text{work}}{\text{Men}\times \text{Days}}\]
    \[\frac{W}{24\times 13}=\frac{W}{20\times D}\]\[\Rightarrow \]\[20\times D=24\times 13\]
    \[\Rightarrow \]   \[D=\frac{24\times 13}{20}=\frac{78}{5}=15\frac{3}{5}days\]