SSC Sample Paper Mock Test-17 SSC CGL Tear-II Paper-1

  • question_answer
    A job can completed by 12 men in 12 days. How many extra days will be needed to complete the job, if 6 men leave after working for 6 days?

    A) 3

    B)  6

    C)  12

    D)  24

    Correct Answer: C

    Solution :

    Work done by 12 men in 6 days\[=\frac{1}{2}\] Remaining work \[=1-\frac{1}{2}=\frac{1}{2}\] 6 men leave the work,            \[\therefore \]Time taken \[=\frac{12\times 12}{6\times 2}=12\]days


You need to login to perform this action.