    X is 3 times as fast as Y and is able to complete the work in 40 days less than Y. Then, the time in which they an complete the work together is

    A) 15 days

    B)  10 days  

    C)  \[7\frac{1}{2}\text{days}\]

    D)  5 days

    Correct Answer: A

    Solution :

    The ratio of efficiency of X and Y to do the work 3E : E \[\therefore \]Time taken to do the work by X and Y= E : 3E Then,    \[3E-E=40\] \[\Rightarrow \]   \[2E=40\] \[\Rightarrow \]   \[E=20\]days \[\therefore \](X + Y)'s one day work \[=\frac{1}{20}+\frac{1}{60}=\frac{3+1}{60}=\frac{4}{60}\] \[=\frac{1}{15}\] Hence, X and Y together complete the work in 15 days.