    If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

    A) 4 days

    B)  5 days  

    C)  3 days

    D)  2 days

    Correct Answer: C

    Solution :

    \[3\,\,m=6\,\,w\] \[\therefore \]\[m+2\,\,w\] \[12\,\,m+8\,\,w=(12\times 2\,\,w)+8\,\,w=32\,\,w\] \[\therefore \] 6 women can do the work in 16 days \[\therefore \] 32 women can do the work in \[\frac{16\times 6}{32}=3\]days