A) 15
B) 10
C) 8
D) 5
Correct Answer: D
Solution :
200 workers do rest of the work in \[40-35=5\]days \[\therefore \]100 workers can-do the remaining work in\[\frac{5\times 200}{100}=10\]days \[\therefore \]If additional workers were not employed, the work would have lasted\[10-5=5\]days be his schedule time.You need to login to perform this action.