    It 8 men, working 9 hours per day can build a wall 18 metres long, 2 metres wide and 12 metres high in 10 days. How many men will be required to build a wall 32 metres long, 3 metres wide and 9 metres high by working 6 hours a day in 8 days?

    A)  25 men

    B)  18 men

    C)  30 men

    D)  16 men

    E)  None of these

    Correct Answer: C