    A men undertakes to do a certain work in 150 days. He employees 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:

    A)  50

    B)  75

    C)  100

    D)  125

    E)  00

    Correct Answer: C