Railways Technical Ability Production Engineering and Planning Question Bank Production Planning

  • question_answer Which of the following input data are needed for MRP?
    1. Master production schedule
    2. Inventory position
    3. Machine capacity
    4. Bill of materials
    Select the correct answer using the codes given below:

    A) 1, 2 and 3                     

    B) 2, 3 and 4

    C) 1, 2 and 4                     

    D) 1, 3 and 4

    Correct Answer: C


adversite


You need to login to perform this action.
You will be redirected in 3 sec spinner