SSC SSC CHSL TIER-I Solved Paper Held on 08.01.2017

  • question_answer
    Prabhat has done \[\frac{1}{2}\] of a job in 12 days. Santosh completes the rest of the job in 6 days. In how many days can they together do the job?

    A)  12 days

    B)  4 days

    C)  8 days

    D)  16 days

    Correct Answer: C

    Solution :

     \[\because \] Prabhat does \[\frac{1}{2}\]work in 12 days. \[\therefore \]Prabhat will do 1 work in \[12\times 2=24\]days. Similarly, Santosh will do 1 work in 12 days. \[\therefore \] One day?s work of Santosh and Prabhat \[=\frac{1}{24}+\frac{1}{12}=\frac{1+2}{24}=\frac{3}{24}=\frac{1}{8}\] \[\therefore \]Required time = 8 days