    10 women can complete a work in 7 days and 10 children take 14 days to complete the same work. How many days will 5 women and 10 children take to complete the same work?

    A) 3                     

    B) 5

    C) 7                     

    D) 9

    Correct Answer: C

    Solution :

    10 women \[\times \]7=10 children\[\times \]14 1 women = 2 children Now, 10 women can complete the work in 7 days. Then, 5 women and 10 children or 10 women will complete the same work in 7 days.