    Directions This section consists of fifty (50) questions. Each question consists of legal propositions principles (hereinafter referred to as 'principle') and facts. These principles have to be applied to the given facts to arrive at the most reasonable conclusion. Such principles may or may not be true in the real sense, yet you have to conclusively assume them to be true for the purposes of this section. In other words, in answering the following questions, you must not rely on any principles except the principles that are given here in below for every question. Further you must not assume any facts other than those stated in the question. The objective of this section is to test your interest towards study of law, research aptitude and problem solving ability even if the 'most reasonable conclusion' arrived at may be unacceptable for any other reason. It is not the objective of this section to test your knowledge of law.
    Principle He, who goes to the court of law to seek justice, must come with clean hands. Facts P enters into a contract with S under which S has to construct a house for P and has to complete the same within one year from the date of the contract. This contract includes two very important terms. According to first term, if there is price hike of the materials to be used in the construction, then the escalation charges at a particular rate shall be payable by P to S. According to second term, if the construction of the house is not completed within the period prescribed for it, then S will have to pay penalty at a particular rate to P. Before the completion of the construction work the workers of S go on strike and strike continues up to three months even after the expiry of one year. After that period workers return   d the construction work again starts. During the last three months period of strike there was a considerable rise in the price of the building material. S claimed escalation cost from P, P did not agree to it. S filed a suit in the court of law either to order the payment of the price of the building material on the basis of escalated price or to allow him to stop the work without incurring any penal liability towards P.

    A)  S will succeed as strike by his workers was unexpected and beyond his control

    B)  S can succeed as there is an escalation clause in the contract

    C)  S cannot succeed as he has failed to complete the construction work in time and strike cannot be treated as a valid excuse for delay in work

    D)  S can succeed, if he pays penalty to P for delay

    Correct Answer: C

    Solution :

    Ans.  In this case, S will not succeed because there was an express condition in the contract that if the construction of the house is not completed within the period prescribed for it, then he will be liable to pay penalty to P. In this case, according to the principle, one who goes to the court of law to seek justice, must come with clean hands, however here S himself is at fault because he could not construct the house within given time frame, so he will not succeed.