    If 30 men do a piece of work in 27 days, in what time can 18 men do another piece of work 2 times as great?

    A)  80 days           

    B)  70 days

    C)  90 days           

    D)  none of these

    Correct Answer: C

    Solution :

    [c] 18 men complete the same work in \[=\frac{30\times 27}{18}=45\,days\] 18 men complete the double work in \[=45\times 2=90\,\,days.\]