8th Class Mathematics Sample Paper Mathematics Sample Paper-6

  • question_answer
    12 men, working 8 hours a day complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required is:

    A) 6                     

    B) 5

    C) 7                     

    D) 9

    E) None of these

    Correct Answer: E