9th Class Mathematics Related to Competitive Exam Question Bank Word Problems Based on Mathematics

  • question_answer
    16 men complete a work in 12 days. They worked for 4 days. To finish the remaining work in 4 days, how many more men should join in?

    A) 16       

    B) 30          

    C) 12      

    D)                                      12

    E) None of these

    Correct Answer: A

    Solution :

    Not Available 