    Match List-I (Methods) with List-II (Problems) and select the correct answer using the codes given below the lists.
    List-I List-II
    A. Moving Average        1. Assembly
    B. Line Balancing         2. Purchase
    C. Economic Batch Size   3. Forecasting
    D. Johnson alogorithm     4. Sequencing
    Codes:

    A) A\[\to \]1, B\[\to \]3, C\[\to \]2, D\[\to \]4

    B) A\[\to \]1, B\[\to \]3, C\[\to \]4, D\[\to \]2

    C) A\[\to \]3, B\[\to \]1, C\[\to \]4, D\[\to \]2

    D) A\[\to \]3, B\[\to \]1, C\[\to \]2, D\[\to \]4

    Correct Answer: D