    Consider the data given in the following table:
    Prod-duction plan Period Demand Regular Prod. Overtime Prod. Others
    1 500 500 ? ?
    2 650 650 150 ?
    3 800 650 150 ?
    4 900 650 150 7
    Give the fact that production in regular and overtime is limited to 650 and 150 respectively, the balance demand of 100 units in the 4th period can be met by:

    A) Using overtime in period 2

    B) Using regular production in period 1

    C) Subcontracting

    D) Using any of the steps indicated in A, B and C

    Correct Answer: D