    Match List-I with List-II and select the correct answer using the codes given below the Lists.
    List-I (Topic) List-II (Method of solving)
    A. Forecasting 1. North-West comer Method
    B. Linear Programming     2. Rowan Plan
    C. Wage Incentive      3. Method of penalty
    D. Work Measurement   4. Time series Analysis
    5. Work Factor System
    Codes:

    A) A\[\to \]4, B\[\to \]3, C\[\to \]1, D\[\to \]5

    B) A\[\to \]4, B\[\to \]1, C\[\to \]5, D\[\to \]3

    C) A\[\to \]4, B\[\to \]3, C\[\to \]2, D\[\to \]5

    D) A\[\to \]3, B\[\to \]1, C\[\to \]2, D\[\to \]4

    Correct Answer: C