  • question_answer Which of the following factors are to be considered for production scheduling?
    1. Sales forecast            
    2. Component design
    3. Route sheet               
    4. Time standards
    Select the correct answer using the codes given below:
    Codes:

    A) 1, 2 and 3                     

    B) 1, 2 and 4

    C) 1, 3 and 4                     

    D) 2, 3 and 4

    Correct Answer: D