    For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break-even r production per month will be:

    A) 300                              

    B) 460

    C) 500                              

    D) 10000

    Correct Answer: C

    Solution :

    \[5000+20\times 500=30X\] \[X=500\]