Railways NTPC (Technical Ability) Production Engineering and Planning Question Bank Production Planning

  • question_answer
    Which one of the following is not a necessary information input to Material Requirements Planning?

    A) Inventory on hand

    B) Bill of materials

    C) Sequence of operations on a job

    D) Master production schedule (MPS).

    Correct Answer: C


You need to login to perform this action.
You will be redirected in 3 sec spinner