Railways Technical Ability Production Engineering and Planning Question Bank Production Planning

  • question_answer Which of the following activities pertain to a master production schedule.
    1. Sizing and timing of specific items, production lot
    2. Sequencing of individual orders of jobs
    3. Short term allocation of resources to individual operations
    4. Product design
    Select the correct answer using the code giver below:

    A) 1, 2 and 4                     

    B) 2, 3 and 4

    C) 1, 3 and 4                     

    D) 1, 2 and 3.

    Correct Answer: C


adversite


You need to login to perform this action.
You will be redirected in 3 sec spinner