Railways Technical Ability Production Engineering and Planning Question Bank Production Planning

  • question_answer In which one of the following types of industrial activities, the problem of loading and scheduling becomes more difficult?

    A) Single-product continuous

    B) Multi-product continuous

    C) Batch production

    D) Continuous or process production

    Correct Answer: C


adversite


You need to login to perform this action.
You will be redirected in 3 sec spinner