Railways NTPC (Technical Ability) Production Engineering and Planning Question Bank Production Planning

  • question_answer
    Match List-I (Activity) with List-II (Technique) and select the correct answer using the code given below the lists:
    List-I (Activity) List-II (Technique)
    A. Line Balancing    1. Value Analysis
    B. Product Development 2. Exponential  Smoothing
    C. Forecasting 3. Control Chart
    D. Quality Control   4. Selective Control
    5. Rank positive Matrix
    Codes:

    A) A\[\to \]2, B\[\to \]1, C\[\to \]4, D\[\to \]3

    B) A\[\to \]5, B\[\to \]3, C\[\to \]2, D\[\to \]1

    C) A\[\to \]2, B\[\to \]3, C\[\to \]4, D\[\to \]1

    D) A\[\to \]5, B\[\to \]1, C\[\to \]2, D\[\to \]3

    Correct Answer: D