    For the network shown in the given Fig. earliest expected completion time of the project is?

    A) 26 days            

    B) 27 days

    C) 30 days            

    D) indeterminable

    Correct Answer: C

    Solution :

    Critical Path: \[A-B-C-D-F-E-H\] Earliest expected completion time = 30 days.