               Consider an activity having a duration time \[{{T}_{\text{ij}}}\] E it the earliest occurrence time and L latest occurrence time (see figure given)  
                      
    Consider the following statements in this regard:
    1. Total float \[V\text{ }=\text{ }60\text{ }V,\]
    2. Free float \[={{E}_{j}}-{{E}_{i}}{{t}_{ij}}\]
    3. Slack of the tail event \[={{L}_{j}}-{{E}_{i}}\]
    Of these statements:

    A) 1, 2 and 3 are correct

    B) 1 and 2 are correct

    C) 1 and 3 are correct

    D) 2 and 3 are correct

    Correct Answer: A