    Match List-I (Welding problems) with List-II (Causes) and select the correct answer using the codes given below the list:
    List-I List-II
    A. Cracking of weld   1. Excessive metal stresses
    B. Cracking of base       2. High joint metal  rigidity
    C. Porosity           3. Oxidation
    D. Inclusions             4. Excessive \[{{H}_{2}},{{O}_{2}},{{N}_{2}}\] in the welding atmosphere
    Codes:

    A) A\[\to \]2, B\[\to \]1, C\[\to \]4, D\[\to \]3

    B) A\[\to \]3, B\[\to \]4, C\[\to \]2, D\[\to \]1

    C) A\[\to \]2, B\[\to \]4, C\[\to \]2, D\[\to \]1

    D) A\[\to \]3, B\[\to \]1, C\[\to \]4, D\[\to \]2

    Correct Answer: A