    A contractor can complete a certain piece w of work in 9 days. He employed certain number of men, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. How many men were originally employed?

    A)  \[12\]                                                  

    B)  \[15\]                  

    C)  \[18\]                                  

    D)         \[24\]

    Correct Answer: B