A) \[x\ge 0,\ y\ge 0,\ 2x+3y\ge 70,\ 3x+2y\ge 75\]
B) \[x\ge 0,\ y\ge 0,\ 2x+3y\le 70,\ 3x+2y\ge 75\]
C) \[x\ge 0,\ y\ge 0,\ 2x+3y\ge 70,\ 3x+2y\le 75\]
D) \[x\ge 0,\ y\ge 0,\ 2x+3y\le 70,\ 3x+2y\le 75\]
Correct Answer: D
Solution :
Type of items | Working time on machine | Man labour |
Shirt (x) Pent (y) | 2 hours 3 hours | 3 hours 2 hours |
Availability | 70 hours | 75 hours |
You need to login to perform this action.
You will be redirected in
3 sec